Start Date:
08/11/16
End Date:
09/22/16
NEW TRAFFIC ALIGNMENT AND INTERSECTION ON NH 111 AND NH 111A IN WINDHAM BETWEEN I-93 AND RANGE ROAD
The New Hampshire Department of Transportation (NHDOT) announces plans to open new portions and shift traffic on NH 111 and NH 111A in Windham on Thursday, August 11, 2016. NH 111 westbound traffic will shift to the reconstructed lanes on the north side and a second lane will be striped and opened for eastbound traffic on the south side. All NH 111A traffic will be diverted to and onto the new signalized intersection and roadway between Klemm’s/McDonalds and the Citizen’s Bank (at NH 111) and The Common Man restaurant.
These operations will utilize lane closures and traffic shifts that may result in minor delays to NH 111/NH 111A traffic. This work is weather dependent and could be delayed due to inclement weather. Message boards, uniformed officers, flaggers, and traffic control devices along NH 111/NH 111A will be used to provide advanced information and direct motorists through the work zone.
In addition Range Road will be closed to thru traffic in the interim between West Shore Road and east of The Common Man; but will remain open for local traffic. This closure will remain in place for approximately 6 weeks while the connector road is constructed in this area.
This work is part of the construction of the final northbound I-93 roadway alignment and northbound ramps in the vicinity of Exit 3 and the Weigh Station. Weaver Bros. Construction of Bow, New Hampshire is the general contractor for the $32.2 million project, which is scheduled for completion in the fall of 2016.