New Hampshire

Ongoing & Upcoming Events

The following is provided to give an update on ongoing and upcoming events. More detailed information can be found throughout the website.

Exit 3 Events on I-93 NB/Route 111A (13933H)

  • October - February 2017 -
    October 2016 - Anticipated final completion.
    February 2017 - Work continues to address punch list items. Minor intermittent traffic control is anticipated to complete punch list items.

Events on I-93 NB and SB between Exits 3 and 4 (14633B)

  • January - February 2017 -
    January 2017 - Blasting work continued along with rock crushing. Paving for the spring traffic shift was completed. Bridge work has begun on the east side of the NB Fordway Ext. Bridge, and will continue. The west side of the NB North Lowell Road Bridge deck has been removed. NB traffic was shifted back to the east from MM 8.2 to MM 10.0, where traffic will stay until the spring. Work resumed on the recreational trail box culvert. The construction of the sound wall base / berm is ongoing.
    February 2017 - Work will continue on the recreation trail bridge. Drilling for the soundwall bases will begin. Crushing of the blasted rock will continue. Bridge work is anticipated to continue at Fordway Extension and NB North Lowell Road. No rolling roadblocks or lane closures are anticipated in the near future.
    October 2019 - Anticipated final completion.

I-93 NB and SB between Exit 5 and the I-293 Split (14633H)

  • January - February 2017 -
    January 2017 – Drainage work and blasting work continued.
    February 2017 – Work on the Cohas Brook Culvert will continue. Drainage installations will continue along with the installation of cofferdams at Long Pond Book and Bodwell Road. Blasting operations will also continue in the southbound direction. Trucks will be accessing the work areas from the mainline shoulders. Rolling roadblocks will be used daily for blasting operations.
    October 2019 - Anticipated final completion.

Exit 3 Park and Ride (10418H)

  • January - February 2017 -
    November 2016 - This contract was awarded to George R. Cairns & Sons, Inc. of Windham, NH.
    December 2016 - Work began.
    January 2017 - Tree clearing and stump removal progressed in preparation for blasting.
    February 2017 – Blasting work could begin, the work will continue as long as the weather permits. No significant traffic impacts or delays are expected.
    October 2017 - Anticipated final completion.

Exit 4 Interchange and NH Route 102 Work (14633D)

  • December 2016 - February 2017 -
    December 2016 - This contract was awarded to R.S. Audley of Bow, NH.
    February 2017 – Tree clearing is anticipated to start.
    Spring 2017 - Work is anticipated to begin on NH Route 102.
    September 2020 - Anticipated final completion.

I-93 Mainline Between Exits 4 and 5 (14633I)

  • November 2016 - February 2017 -
    November 2016 - The project was advertised for bids.
    December 2016 – Bids were received.
    Spring 2017 - Work is anticipated to begin.
    August 2019 - Anticipated final completion.
 
copyright 2004 New Hampshire DOT NH.gov | privacy statement | accessibility policy | site map | contact us