New Hampshire

Ongoing & Upcoming Events

The following is provided to give an update on ongoing and upcoming events. More detailed information can be found throughout the website.

Exit 3 Events on I-93 NB/Route 111A (13933H)

  • October - July 2017 -
    October 2016 - Anticipated final completion.
    July 2017 - Work continues to address punch list items. Minor intermittent traffic control is anticipated to complete punch list items. Work is anticipated to be complete in July.

Events on I-93 NB and SB between Exits 3 and 4 (14633B)

  • March to July 2017 -
    March to May 2017 - Blasting work continued along with rock crushing. The construction of the sound wall was completed and included drilling and installing the soundwall bases and the installation of the wood panels. Work was completed on the northbound Fordway Extension Bridge and the North Lowell Road Bridge. Southbound traffic was shifted to the northbound barrel.
    June to July 2017 – Blasting and rock crushing will recommence. The majority of the work will take place on the former southbound barrel outside of traffic. Work continues on the pedestrian box culvert. Rolling road blocks will be in place to help facilitate blasting operations on northbound and southbound I-93.
    October 2019 - Anticipated final completion.

I-93 NB and SB between Exit 5 and the I-293 Split (14633H)

  • March - July 2017 -
    March to May 2017 – Work on drainage, blasting, tree clearing continued. Work on the Cohas Brook Culvert continued. Work on the soundwalls progressed. Roadway work on the roadway for the southbound and northbound barrel began.
    June to July 2017 – Blasting operations will continue. Rolling roadblocks will be used daily for blasting operations.
    October 2019 - Anticipated final completion.

Exit 3 Park and Ride (10418H)

  • March to July 2017 -
    March to May 2017 – Blasting work began. Base course materials, embankment, humus and drainage were complete along the future NH Route 111 access road.
    June to July 2017 – Base course materials, embankment, humus and drainage are proposed to be installed on the northern half of the parking area a. No significant traffic impacts or delays are expected.
    October 2017 - Anticipated final completion.

Exit 4 Interchange and NH Route 102 Work (14633D)

  • March to July 2017 -
    March to May 2017 – Work began on NH Route 102 with and with work on the new NH Route 102 bridge. This work included tree clearing, blasting, and drainage installation. Work progressed along I-93 Northbound including work on the Kendall Pond Road Bridge and utility work. Work on Ash Street has also begun including the installation of a temporary signal on Ash Street to facility traffic control operations while work is completed to replace the Ash Street Bridge.
    June to July 2017 - Daily rolling road blocks for blasting, daily shoulders closures on I-93 NB and SB Mainline for clearing access. Night work lane closures and daily shoulder closures on I-93 NB and SB Mainline for truck access. NH Route 102 and Ash Street will have lane closures. The Ash St/Pillsbury Road Bridge temporary signal will be active for the construction season.
    September 2020 - Anticipated final completion.

I-93 Mainline Between Exits 4 and 5 (14633I)

  • March to July 2017 -
    March to May 2017 - The project was awarded to Weaver Brothers Construction Company from Bow NH. Work began with tree clearing, utility work, and the construction of drainage. Blasting, rock crushing and bridge work at Stonehenge Road also began. To facilitate future construction, temporary roadway widenings on I-93 were constructed.
    June to July 2017 – Blasting, rock crushing and tree clearing will continue. In addition, work will continue at the Stonehenge Road Bridge. Daily rolling roadblocks starting at Exits 4 and 5 approaching the project will be utilized during blasting operations.
    August 2019 - Anticipated final completion.
 
copyright 2004 New Hampshire DOT NH.gov | privacy statement | accessibility policy | site map | contact us